How to Build a Wood Ground Level Boardwalk Or Patio

There are many occasions after a rain that yourbar-b-que grille and some chairs and a table, your
yard is not usable since the grass is wet andjoist spacing can be sixteen (16) inches on
soggy. Warm overcast summer days are a loss ifcenters. If you expect heavier loads go for
you and the kids are stuck in the house. You cantwelve inch centers. Layout all the joists in their
of course use patio block, poured concrete orrespective areas including the rim or end joists. It
stone to make your patio but wood seems to beis best to create the exterior box or rim joists
a softer, warmer material to work with. You canfirst and get them set level. Nail or screw all the
add a ground level wood patio for less than aperimeter joists together. Screws are preferable
deck would cost and extend the number of daysas you will not be able to add fasteners after the
you can grille or just sit outside and enjoy thejoists are buried and the decking is applied. Using
summer months.your two foot framing square, make sure the
You will need a fairly flat area to build your patiobox is as perfectly square as you can make it.
pretty much the same as if it was concrete orMeasure corner to corner to assure these
stone. Some minor hand grading can be done butmeasurements are exactly the same. If they are,
if you need to use heavy machinery, the area isthe box is square. Now using the level and tape
probably more suited to a raised deck than ameasure, take measurement shots at the four
patio. You will need to have a builder's level andcorners and assure they are all exactly the same.
tape measure to set some elevations for theYou may have to dig a little or add some dirt
tops of the floor joists as you install them. If youunder the joists but make sure if you are adding
are planning a great many yard projects you maymaterial under the joists that the dirt is
want to consider buying a builders level instead ofcompacted firmly. You do not want the deck to
renting. One or two days of extra rental feessettle later.
because you forgot to return it can pay for theNow that the perimeter box is level and square
level itself.you may start adding the rest of the floor joists.
Setup the level and make sure it is perfectly levelThe use of Teco hangers or other types of joist
in all directions by adjusting the screws. Make surehangers is not really required as the patio is
the built-in bubble level is level in all directions asground level and the joists will be supported their
you turn the head itself.entire length by the ground below. If you have
Starting in any corner of the patio, take elevationthem and want to use them that is fine. Continue
shots in all four corners. For this example we willframing and constantly checking that the entire
assume your first shot is 5'-0" on your tape.assembly has remained level and square. Once the
Looking through the level glass, the left-to rightframing is done, back fill all the joists with as
cross hair is exactly at 5'-0" or sixty inches. Nowmuch materials as available that you removed in
read the other three corners. We get readings ofthe beginning. Remove any really large rocks
4'-10", 5'-3" and 5'-2". This means the patio area isunless you can bury them well below the bottoms
fairly flat and by adding or deducting the shotof the decking boards.
measurements from the original 5'-0" we seeI know you want to start installing the decking
there is only a maximum of three inches in heightboards now but first we are going to run some
difference to the high point and we may need tolandscape wiring under the deck. Figure out where
fill in two inches or so at the low point. Take ayou want to add some low voltage lighting, even
couple more shots in the middle area of the patioif it is in the future, and run the wires now. It will
to make sure there are no real high points or lowbe near impossible later on ot travel under the
spots that will cause major hand work to level.deck and you will use a lot less wire going from
Our sample wood patio is going to be ten feet bycorner to corner under the joists instead of
ten feet in size. If at all possible you want to usearound the outside of the patio. I installed four
one piece floor joists as they will result in lessthree foot 4" x 4" posts in the corners and ran
framing work and you only need to set the levelthe wire up the posts for future lights keeping the
grade at both ends of the joist. Once the endsends where I planned to place the low voltage
are set, you can either fill in the middle to supporttransformer.
the joist or dig out a little to allow the joist to sitIf you installed your floor joists on sixteen inch
on the level pads at both ends. Remember wecenters, you must use 2" thick (nominal 1 5/8")
are not digging out the entire patio. You only digmaterials for the deck boards. If you used twelve
out enough to let the joists sit level with perhapsinch centers you may also use 5/4" thick decking
a three inch wide trench. Once the joists are allboards.
set level and the perimeter joists are installed,Using twelve inch joist centers also allows you to
you will back fill all the loose dirt against the joistsinstall your boards on a bias and create interesting
themselves. Nothing to haul away! If you weredesigns in the boards themselves. Placing some
somewhat neat with your work by placing all yourboard areas on diagonals to others can create
excavated material inside the patio area, the onlymany different designs. I strongly suggest that
evidence of digging will be the small slit youyou use galvanized deck screws to install the
created around the edges of the patio for thedecking boards. Screws will not pull loose over
perimeter joists. These areas will fill in with lawntime as will nails. Screws also provide a tighter
very quickly.overall assembly when completed.
A ground level patio requires that all wood beWhen you start your first deck board, have the
pressure treated or other type of woodfirst board hang over the edge of the perimeter
acceptable for ground contact. Most if not alljoist approximately one inch. This provides a nice
building departments do not require a permit for ashadow line and any bowing on the joist below will
patio but you should ask if one is required. Benot be noticeable. Make sure you allow enough
sure to be very clear that this is a patio and notboard on the opposite side of the deck so the
a deck. There are no footings, no supportlast board will also hang over the same amount.
columns or beams and is not connected to aDo this on all four sides. Do not cheat on the
structure. In areas that have frost and freezingamount of screws you use. If you are working
temperatures, the inspector wants to be sure noalone, even with the best quality screw gun, this
damage will result from heaving in thework can be very tiring. Take a break or two or
freeze--thaw cycles. Since the patio is freecome back the next day to finish. If you have a
standing there will be no damage to structures.helper, pre-drilling holes for the screws saves tons
There are some areas that due to local Zoningof arm stress and will help prevent splitting of the
regulations require permits for just aboutboards.
everything you do on your property so it alwaysCurved areas can be built with a little extra
best to ask first.framing to support the decking and look fantastic
A minimum floor joist size should be 2' x 6" PTwhen done. If you are creating a walkway to the
but I prefer 2" x 8" PT for the extra rigidity thepatio the same framing methods as the patio are
wider boards provide. If you can get the smallerused. The framing underneath is straight and
lumber at a great discount or perhaps used orsquare but by cutting the decking on a curve you
free it may be worth the extra time to install acan create some really eye pleasing effects. My
series of wood blockings to stiffen the deck. Ifsecond patio but next to my first is seven inches
you are going to place a hot tub on the patio,lower and twice as big. After heavy rains when
stay with the larger lumber to prevent futureothers are waiting for their lawns to dry out, we
sagging of the joists.can go out and sit or cook and have a dry place
If your patio is going to be for general use for ato enjoy minutes later.